The first neighborhood slated for the work is located on each side of Neroly Road between Oakley Road and Regal Court. Around April 12, the contractor will transition to the other neighborhood, located north of Main Street and encompassing Teresa Lane, Charles Way and Miguel Drive.
The latter neighborhood includes the first phase of SierraCrete remediation that the city has undertaken. On streets with SierraCrete, the severely cracked pavement sections will be excavated to native material and then reconstructed with traditional base rock and asphalt. In areas where the asphalt has not failed, the SierraCrete will be left in place.
For more information, call Jason Kabalin at 925-625-7040 or Nancy Marquez at 925-625-7007.