Civic center reaches for the sky
by Rick Lemyre
Apr 15, 2010 | 1126 views | 0 0 comments | 14 14 recommendations | email to a friend | print
Workers began to install structural steel beams for the new Brentwood civic center this week.<br><i>Photo by Richard Wisdom</i>
Workers began to install structural steel beams for the new Brentwood civic center this week.
Photo by Richard Wisdom
slideshow
Workers began to install structural steel beams for the new Brentwood civic center this week.<br><i>Photo by Richard Wisdom</i>
Workers began to install structural steel beams for the new Brentwood civic center this week.
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
<i>Photo by Richard Wisdom</i>
Photo by Richard Wisdom
slideshow
It might be said that Brentwood’s new civic center got off the ground when planning began several city administrations ago, or perhaps when it received final approval last year. Perhaps it occurred when the ceremonial groundbreaking was held, or when the fencing and bulldozers actually arrived.

In any case, “getting off the ground” took a new, literal meaning this week when the first massive, structural steel beams were carefully put in place, and the $36 million project began climbing toward the treetops.

“Everyone is very excited,” Assistant City Manager Karen Chew said Wednesday of the project going vertical.

According to Chew, the recent rains “held us up a little, but they think they’re going to be able to catch up.” The project is scheduled for completion in late 2011.

The first steel beams to go up, those closest to Second Street along Maple, are for the new Council Chambers. After that come the beams for city hall, farther east on Maple, then the community center, along Oak Street. The structural steel work should take a total of about six weeks to finish, Chew said.

Chew said the last thing built would be the parking structure, bids for which were opened this week. Chew said the bids needed more evaluation, but it appears they will be “in the ballpark” of $11 million, as planned. Including the parking structure, re-vamping of City Park and other civic center components, the project’s entire cost will be $47 million.

Chew said no significant problems had cropped up, with the exception of one of the live oak trees that was relocated late last year. Two of the 28-ton, 20-year old trees were moved across the park to make room for the civic center, and one of them isn’t looking well.

“There’s still some signs of life,” Chew said. “They’re not ready to take it out and start over yet.”
Comments
(0)
Comments-icon Post a Comment
No Comments Yet
Postings are not edited and are the responsibility of the author. You agree not to post comments that are abusive, threatening or obscene. Postings may be removed at the discretion of thepress.net.